Monday, 16 January 2012

Day 205 - Basement fit-out starts

Preparing the basement floor for the 110mm insulation

Basement sump pits (shower + fail safe)

Day 203 - More wires and pipes!

Data and AV cables at the rack location



Heat recovery venting and central vacuum pipes in the kitchen
AV wiring for the TV room in the basement

Saturday, 7 January 2012

Day 196 - The peach house!

External renders boards going up - a nice peach colour!


Day 193 - First fix nearing completion

The cisterns for the wall hung toilets are in























Secondary insulation and UFH complete























Bathroom fittings and ceilings done


MHRV unit in the basement (and one in the loft!)

Ducting for the ventilation system in the basement ceiling