Sunday, 19 February 2012

Day 239 - Outside taking shape

Frontdoor and sidelight fitted Really pleased with the look.

Two base coats of render done.  Top coat next week.

Day 239 - First fix comes to an end

Lounge, looking towards the Study

Kitchen floor screeded and walls and ceiling boarded

Master bedroom

Master En-suite shower area









First floor landing looking north to Bed2


Bed 3, brightest room in the house
First floor landing looking south towards Bed1 and Bathroom

Monday, 16 January 2012

Day 205 - Basement fit-out starts

Preparing the basement floor for the 110mm insulation

Basement sump pits (shower + fail safe)

Day 203 - More wires and pipes!

Data and AV cables at the rack location



Heat recovery venting and central vacuum pipes in the kitchen
AV wiring for the TV room in the basement

Saturday, 7 January 2012

Day 196 - The peach house!

External renders boards going up - a nice peach colour!


Day 193 - First fix nearing completion

The cisterns for the wall hung toilets are in























Secondary insulation and UFH complete























Bathroom fittings and ceilings done


MHRV unit in the basement (and one in the loft!)

Ducting for the ventilation system in the basement ceiling

Monday, 5 December 2011

Day 163 - First floor first fix nearing completion

Wiring, plumbing and underfloor heating completed

MHRV ducting this week and then on to wall linings next

Monday, 14 November 2011

Day 144 - Windows complete

   

Large window in the hallway void hoisted in to position

Pool house doors and window in

Sunday, 13 November 2011

Day 143 - Zinc roof and getting ready for first fix

Zinc covering to pitched roof complete

Flat roof ready for the tapered insulation to be fitted

Inside all battened out ready for the services

Cara-Lee trying out the staircase