Friday, 23 March 2012

Day 269 - Kitchen fit starts, glass balustrades arrive

Kitchen island and sink run base units in place...

..and templated for the stone work surface.
Glass balustrade fixed to the front balcony.
Staircase getting prepared for cladding

Wednesday, 14 March 2012

Day 262 - Good progress inside and out

Back of the house with the scaffolding down


Groundworks progressing, wall built and drainage laid
Door blanks being prepared before offsite spraying

Family bathroom tiling in progress

400 litre tank and ASHP unit in plant room

Sunday, 4 March 2012

Day 253 - Scaffolding down, tiles up

Scaffolding down ready for the wood cladding next week

Basement much brighter now the scaffolding is down



Kitchen ceiling plastered and floor screeded

Master Ensuite tiling in progress


Bath plumbed and ready for tiling in the Family Bathroom

Landing skimmed and ready for decorating

Bed3 ready for decorating

Sunday, 19 February 2012

Day 239 - Outside taking shape

Frontdoor and sidelight fitted Really pleased with the look.

Two base coats of render done.  Top coat next week.

Day 239 - First fix comes to an end

Lounge, looking towards the Study

Kitchen floor screeded and walls and ceiling boarded

Master bedroom

Master En-suite shower area









First floor landing looking north to Bed2


Bed 3, brightest room in the house
First floor landing looking south towards Bed1 and Bathroom

Monday, 16 January 2012

Day 205 - Basement fit-out starts

Preparing the basement floor for the 110mm insulation

Basement sump pits (shower + fail safe)

Day 203 - More wires and pipes!

Data and AV cables at the rack location



Heat recovery venting and central vacuum pipes in the kitchen
AV wiring for the TV room in the basement

Saturday, 7 January 2012

Day 196 - The peach house!

External renders boards going up - a nice peach colour!


Day 193 - First fix nearing completion

The cisterns for the wall hung toilets are in























Secondary insulation and UFH complete























Bathroom fittings and ceilings done


MHRV unit in the basement (and one in the loft!)

Ducting for the ventilation system in the basement ceiling

Monday, 5 December 2011

Day 163 - First floor first fix nearing completion

Wiring, plumbing and underfloor heating completed

MHRV ducting this week and then on to wall linings next

Sunday, 27 November 2011