Saturday 16 July 2011

Day 26 - Excavation and welding of the tops of the sheet piles


Sheet piling excavated and the exposed tops welded on both sides in preparation for the reenforced concrete ring beam.



Part one of the surface water drainage, the 6500 litre concrete tank which will then flow into the crate system below.


The soil percolation test results were so poor hence the design of the elaborate soakaway.